Skip to content Skip to footer

PROJECT NAME: CONSTRUCTION WORKS FOR PIPELINE 20” RTR UNDERGROUND
WITH 3 VALVE STATION FROM SDG TO ABQAIQ PLANT-141AND WITH 3 HDD.

PROJECT SUMMARY :
Supply and apply for 20″ Raw Water Pipeline In plant various CS piping as supply and apply inside Abqiq Plant
32 nos. Tie-ins Civil work (excavation, concrete, thrust boring work …other)
Electrical & Instrumentation work Equipment installation (diesel generator, valves station, pannel boards, isolation valves … other)
Precomissioning and commissioning support

END USERSAUDI ARAMCOPROJECT TYPELSPBShare